In June, 2023, City Council debated whether they should repair, renovate, build new, or relocate City Hall. In September, 2023, City Council made the decision to renovate City Hall. Great Plains Asbestos Control of Kearney began removal of asbestos-containing materials and mold remediation in the City Hall building at 220 N. Hastings Ave., in late 2023. Asbestos removal and mold remediation is slated to be complete in February. Hastings City Council members discussed during their Feb. 19, 2024 work session design options for the council chambers and building exterior.
Design plans are scheduled to be complete around April. Interior demolition is anticipated to be complete around May. Construction is scheduled to start around August and be completed around March 2026.
This is a tentative timeframe and subject to change for a variety of reasons.
City Hall, known for its white marble exterior, was constructed in 1963 for use as a bank. The City of Hastings acquired the property in 1984 and has used it to house various municipal offices since that time.
In addition to the council chambers, City Hall is also home to the administration, development services and finance departments.
Renderings of the exterior are included below. The different renderings are included under our "Documents" to the right.
Please take the time to provide feedback below, including voting on exterior and council chamber options. Subscribe to stay informed.
Hastings City Hall exterior option 1
Hastings City Hall exterior option 2
In June, 2023, City Council debated whether they should repair, renovate, build new, or relocate City Hall. In September, 2023, City Council made the decision to renovate City Hall. Great Plains Asbestos Control of Kearney began removal of asbestos-containing materials and mold remediation in the City Hall building at 220 N. Hastings Ave., in late 2023. Asbestos removal and mold remediation is slated to be complete in February. Hastings City Council members discussed during their Feb. 19, 2024 work session design options for the council chambers and building exterior.
Design plans are scheduled to be complete around April. Interior demolition is anticipated to be complete around May. Construction is scheduled to start around August and be completed around March 2026.
This is a tentative timeframe and subject to change for a variety of reasons.
City Hall, known for its white marble exterior, was constructed in 1963 for use as a bank. The City of Hastings acquired the property in 1984 and has used it to house various municipal offices since that time.
In addition to the council chambers, City Hall is also home to the administration, development services and finance departments.
Renderings of the exterior are included below. The different renderings are included under our "Documents" to the right.
Please take the time to provide feedback below, including voting on exterior and council chamber options. Subscribe to stay informed.
Share Do you think it is going to be more expensive than anticipated? on FacebookShare Do you think it is going to be more expensive than anticipated? on TwitterShare Do you think it is going to be more expensive than anticipated? on LinkedinEmail Do you think it is going to be more expensive than anticipated? link
Do you think it is going to be more expensive than anticipated?
Admin
asked
11 months ago
Until we have plans and specifications complete and receive bids, it is too early to tell.
Share Public entrance is to the east???? on FacebookShare Public entrance is to the east???? on TwitterShare Public entrance is to the east???? on LinkedinEmail Public entrance is to the east???? link
Public entrance is to the east????
Kimma Thayer
asked
9 months ago
Yes, the public entrance will be on the east side of the building off the parking lot.
February 2024 - Asbestos Removal/mold remediation completed. City Council decides on renderings of building exterior and council chambers.
City Hall Renovation has finished this stage
Design open house March 4, 2024
City Hall Renovation has finished this stage
Provide input about the proposed designs during an open house, 4-6 p.m. Monday, March 4, at the Hastings Municipal Airport, 3300 W. 12th St.
March 11, 2024 City Council
City Hall Renovation has finished this stage
At the March 11, 2024 City Council meeting. The City Council approved the exterior design Option #1 and interior options with darker wood and darker backdrop for City Hall Design.
August 13, 2024 - Start of demolition
City Hall Renovation has finished this stage
O'Neill Transportation & Equipment of Grand Island began interior demolition of the City Hall building.
August 26, 2024 City Council approval
City Hall Renovation is currently at this stage
City Council approved contract with Genesis Contracting Group of Lincoln NE for $7,092,000 for complete renovation of the interior & exterior of building.
December 31, 2025 Anticipated Completion
this is an upcoming stage for City Hall Renovation