Construction Monthly Progress and Locations
Main and Non-Lead Service Connection Crew:
Contractor waiting on HU Lead Water Service Replacement Crew to finish up on Boston Ave. Once they are done, contractor will abandon old main. This should be done by mid-month (Oct).
One block of water main to go on New York Ave. Then contractor will work on non-lead service tie overs to new main through Oct.
Budget was approved to move next to Garfield Ave. B Street to E Street and 6th Street East Side Blvd. to 2nd Ave. Bid process fall/winter work to start spring 2025 tentatively.