Construction Monthly Progress and Locations

Main and Non-Lead Service Connection Crew:

Boston Avenue is all complete except for one connection to the old main. Work will be complete in November.

The new water main is installed on New York Avenue from A to E Streets. Contractor will work on water service connections to the new main through November.

Hastings Utilities’ lead water service replacement crew will be starting on replacing lead services on New York Avenue, Starting at A Street and moving to E Street.

Budget was approved to move next to Garfield Ave. B Street to E Street and 6th Street East Side Blvd. to 2nd Ave. Design and Bid process Fall/Spring, construction to start spring 2025 tentatively.

Share Construction Monthly Progress and Locations on Facebook Share Construction Monthly Progress and Locations on Twitter Share Construction Monthly Progress and Locations on Linkedin Email Construction Monthly Progress and Locations link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>